Warehouses · Bhiwandi, Mumbai
Kalyani Logistics Park
Four Grade-A warehouses with 12 m clear height, FM2 laser-screeded floors and 64 dock levellers.
7 months
to first go-live

The brief
Black cotton soil up to 4 m deep and a client go-live date fixed to the festive season.
How we built it
Soil replacement with a geogrid mattress, pre-engineered steel buildings erected in parallel with floor pours, and racking installed bay by bay.
The result
First warehouse operational in 7 months; all four in 11.
Before and after
BeforeAfter
Drag the line

BeforeAfter⟷
Kalyani Logistics Park
Open project →BHIWANDI, MUMBAI · 11 MONTHS
Timeline
11 months
Feb 2024Soil replacement
May 2024Floor pours start
Sep 2024Warehouse A live
Jan 2025All four complete