The brief
Over 1.2 lakh vehicles a day below, with no full closures allowed.
How we built it
Precast segments cast off-site and launched at night with an overhead launching girder; traffic diversions moved in 400 m stretches.
The result
Opened to traffic in 30 months with no day-time closures.
Before and after
BeforeAfter
Drag the line

BeforeAfter⟷
Hosur Road Elevated Corridor, Package 2
Open project →HOSUR ROAD, BENGALURU · 30 MONTHS
Timeline
30 months
Jan 2022Piling
Oct 2022Casting yard live
Mar 2023First span launched
Jun 2024Deck complete
Jul 2024Opened